3. HURRICANES AND PIPE DREAMS

L
urching out of the gate, the agency committed some costly missteps in its early days. Two of them occurred in Florida.

In the Florida Keys, some 700 world war veterans, among the remnants of the Bonus Army, were building a road that paralleled Henry Flagler’s rail line to Key West. It was part of the push to increase Key West tourism that had seen Civil Works Administration workers cleaning up the town itself. The road job, sponsored by the Florida Highway Department, had started under FERA and was to be transferred to the WPA.

As Labor Day weekend approached, hurricane warnings went up over the Keys. As the storm bore down, a train was assembled in Miami to evacuate the workers from the camps where they were living, many with their families. One was on Windley Key and two on Lower Matecumbe Key, about eighty miles south of Miami. The train left Miami a little after 4:00
P.M.
on Labor Day, September 2. It steamed south to Homestead under darkening skies. In Homestead, near where the mainland gave way to the curving string of islands, the engineer reversed the train and backed a string of empty coaches down the rails across islands where the trees were flattened by the wind and over bridges lashed by crashing waves. Night fell and the winds grew even stronger as the train chugged deep into the danger zone. It had reached Islamorada on Upper Matecumbe Key when a wall of water seventeen feet high surged over the island and swept the coaches off the rails. Only the engine, Number 447, survived the tidal wave. The wave and winds as high as 200 miles an hour ripped the flimsy workers’ camps apart. Some of the veterans had tied themselves to trees or to boats at anchor as the winds rose. Most of them didn’t make it. The hurricane’s narrow path spared Miami to the north and Key West to the south, but it killed more than 420 people in the Upper Keys—most of them veterans and their wives and children.

Hopkins immediately sent $200,000 for cleanup and relief to Florida. WPA and CCC workers and volunteers plunged into shredded mangrove thickets to look for bodies and found them bloated and deteriorating in the late summer heat, lying in the shallow water or in the trees they had tried to cling to for safety. Governor David Sholtz hinted that the rescue train had not been sent soon enough. “Grand carelessness somewhere was responsible for the tragedy,” he said.

Hopkins’s first response was to blame the weather forecasts: “I don’t think, from reading those weather reports, that anybody would necessarily have evacuated those people,” he said. But the weather reports had been accurate enough to persuade a Florida State Highway Department supervisor to move his equipment to high ground and tie it down, and an outcry rose from veterans groups, including the American Legion. Hopkins sent Aubrey Williams to conduct an investigation. When Williams concluded that the disaster was an “act of God” beyond any “human factors,” the veterans groups and others, including Key West resident Ernest Hemingway, dismissed his report as a whitewash. The novelist’s indignation produced a scathing piece that he wrote for the Communist Party USA journal
New Masses,
implying that Roosevelt and the New Deal were guilty of manslaughter for sending the veterans to the Keys and keeping them there during hurricane season.

The WPA’s credibility was not much harmed by Hemingway’s fulminating in a Communist house organ; if anything, criticism from the left counterbalanced the generally harsher attacks coming from the right. But the start-and-stop history of another project in the state had the potential to do much greater damage. This project was the Florida Ship Canal, an overreaching effort to dig a route for deepwater shipping across the peninsula of Florida from the Atlantic Ocean to the Gulf of Mexico. It was a lobbyist’s creation, promoted by business and banking interests in Jacksonville, which would be the canal’s Atlantic entry point, and it had some military backing, since a canal would allow tankers carrying Texas oil to reach East Coast refineries without going around Florida’s “hurricane-blistered thumb.” It would also protect them from submarine attacks, a form of naval warfare that had emerged during the world war. Such a project normally would have fallen under the War Department budget as approved by Congress, but the day after the Labor Day hurricane struck the Keys, the White House announced a $5 million grant of work-relief funds to jump-start work on the canal.

This was a pittance compared to its eventual cost, projected at nearly $143 million, with construction estimated to take several years under the supervision of the U.S. Army Corps of Engineers, which was responsible for projects on navigable waterways. WPA projects generally were expected to start and end within a single fiscal year, but Roosevelt was eager to push it forward. Moreover, it would employ 6,000 or more men, a high percentage of them from relief rolls, when the job was fully under way.

The canal work attracted laborers from as far away as New York and California to Ocala, the small farm town in north-central Florida where the work was centered. Their first paychecks, distributed on September 17, were a bonanza for Ocala merchants. The J. C. Penney store downtown cashed 700 checks in ninety minutes. Work clothes and boots flew out the door. The butchers at the A&P and Piggly Wiggly couldn’t cut steaks and pork chops fast enough, and quickstepping stock boys wore themselves out keeping potatoes in the produce bins and filling the shelves with cans of pork and beans. Fred Malaver waited on a customer at his clothing store who told him, weeping, that it was the first paycheck he had seen in six months.

Two days later, on September 19, the canal got its official kickoff with a ceremonial dynamite blast triggered by Roosevelt himself from his home in Hyde Park, using a special telegraph keyboard covered with nuggets from Alaska’s Klondike gold rush; it had been used by presidents since William Howard Taft to launch significant events. By the following Tuesday, September 24, 3,000 men were on the job and the project faced a labor shortage. WPA officials in Jacksonville issued an ultimatum: men who refused to leave their homes in other counties to live in the tent camps along the route and work on the canal would be ineligible for any jobs with the WPA. Yet even as merchants restocked for the second WPA payday, the future of the canal appeared to be in trouble.

Lieutenant Colonel Brehon Somervell, supervising the project for the Corps of Engineers, went to Washington on October 1 to say he was going to be out of money. The work was going so fast, he told the chief of engineers, that his initial $5 million would run out by the end of the year, and he needed another $20 million. Meanwhile, farmers around Ocala claimed the canal would admit seawater to the Florida aquifer, the state’s source of fresh water, and harm both crops and drinking water.

At the same time, a new source of opposition was developing. The Rivers and Harbors Act of 1899 affirmed one of Congress’s most jealously guarded prerogatives, the power of the purse. It prohibited the construction of any bridge, dam, dike, or causeway over or in navigable waterways of the United States without the approval of the Congress. Roosevelt’s allotment of relief funds to begin construction of the ship canal did not alter that prerogative; it merely bypassed it temporarily. And on February 10, 1936, the House Appropriations Committee carved $12 million Roosevelt had requested for the ship canal out of the War Department’s appropriations bill.

In the short term, work continued under previously signed contracts; almost 7,000 men worked alongside big draglines and earthmovers to excavate and groom the canal route. But more bad news followed swiftly. On March 17, the Senate voted with the House against the ship canal. A second vote, set up by a call for reconsideration, also failed. Roosevelt could smell defeat. On March 19, he sent Hopkins a memorandum saying, “I am inclined to think that we should take immediate steps to stop the relief workers now on the canal, or at least have them try to do permanent, useful work, such as clearing the lands” along the right-of-way.

On April 10, with a new relief request of $1.5 billion before the House Appropriations Committee, Hopkins promised committee members that none of the money would fund further work on the canal. Roosevelt, five days later, affirmed that he would give it no more money without specific approval from the Congress.

There was one final effort at revival, a proposal to place the canal’s fate in the hands of an independent study group of engineers, but it too failed. Republican senator Arthur H. Vandenberg of Michigan, the chief opponent of the project, scoffed at the “pipe dreaming on the phantom Florida canal” and said there was never any justification for it.

Almost as quickly as it had become a boomtown, Ocala became a backwater again. Employment on the ship canal stood at 2,750 at the end of May, but the
Ocala Star
reported that by August, the only workers left would be caretakers and watchmen.

In Washington, Hopkins and his aides salvaged what they could from the abandoned project. More than $5 million had been spent with no discernible return, but the administration wanted to report something positive, since the country would soon be waking up to the fact that it was an election year. Eventually Hopkins was able to turn the buildings constructed in Ocala to serve as a headquarters for the canal into a WPA-sponsored vocational school, and the political fallout was kept to a minimum.

The huge earthmoving machines that worked on the canal were either dismantled and moved or left to rust. A big steam-powered dragline abandoned near Dunnellon became a boys’ plaything. When it was operating, men had fed six-foot logs into its firebox to keep its big bucket clawing out the earth. Now the bucket was drawn up and locked at the end of its ninety-foot boom, but the machine’s pivot point was unsecured. A few boys pushing could make the cab and boom spin over its earthbound treads, so some would climb up the boom and ride the bucket while their friends pushed them in a circle over the sandy landscape that was once again sprouting with weeds and oak and pine saplings. And with the moldering equipment and revegetating landscape came a political reminder that the president would disregard at his peril in the future—that to ignore the Congress was to invite its opposition.

4. A LODGE AT THE TIMBERLINE

F
ar to the west, in Portland, Oregon, skiers attracted to the snowy escarpments of 11,239-foot Mount Hood had been kicking around the idea of building a ski facility on the mountain since at least the 1920s. At first it was just a shelter where they could take overnight respite. But in 1926 the U.S. Forest Service decided it wanted to attract more visitors to the million-acre Mount Hood National Forest, which stretched south from the Columbia River through sixty miles of mountains, streams, and woodlands, and started sketching drawings for a lodge for skiers and mountain climbers and trying to find funds to build it. In 1934, a group of well-to-do local skiers formed the Mount Hood Development Association to support construction of a lodge. With that, two of the elements needed to push the idea forward were in place.

And the creation of the WPA produced the third component.

Emerson J. Griffith was Oregon’s WPA administrator. Griffith, who was fifty in 1935, was a California native with a dapper thin mustache. He had married well, and spent the early part of his career as a newspaper reporter before setting up a steamship brokerage and shipping agency, the profits from which allowed him and his wife to travel and improve their bridge games. They also allowed Griffith to become active in Democratic politics; he headed Al Smith’s Oregon campaign in 1928, and Roosevelt’s in 1932, and was the state Democratic treasurer both years. After taking the WPA job, Griffith fit into the Hopkins mold, laboring to keep Oregon’s WPA administration free of party hacks. He was also probably the only WPA administrator to have authored a mystery novel, 1933’s
The Monkey Wrench,
which he wrote with his wife during a trip around the world.

Griffith, a skier himself, knew of the efforts to locate a ski lodge on the south face of Mount Hood. When the Forest Service stepped up as the sponsoring agency and the Mount Hood Development Association sold $12,290 worth of bonds to finance the purchase of plumbing and electrical supplies and other materials, thereby allowing the WPA budget to be spent on labor, the proposal advanced quickly.

The Advisory Committee on Allotments approved funding for the lodge in December 1935. It was WPA project number 1101. The budget of $275,513 included a grant of $246,893 from the WPA, a “public donation” of $20,000 from the Mount Hood Development Association, and $8,620 from the Forest Service for truck and machinery rentals.

Linn Forrest was among the many architects hit hard by the depression. He had earned only $120 in 1932, and with a wife and young child to support, he had taken a job with the Forest Service designing fire watch towers and ranger stations. It was late in 1935, as he later recalled, that the Forest Service’s regional engineer, Jim Franklin, came into the office Forrest shared with two other architects and asked them all a question: how much would they spend to build a lodge at the timberline?

Forrest answered, “Nothing.” He had been to the timberline, more than two-thirds of the way up the mountain at 8,540 feet. Above it, bare rocky crags rose to a spectacular peak, while below, the pine forest softened the steep landscape. It was beautiful but barely accessible, and he thought the lack of access would keep visitors away.

But with the WPA’s approval in hand, the Forest Service architects began a series of drawings that shuttled back and forth between them and Griffith at the state WPA headquarters in Portland. Gilbert Stanley Underwood, an architect with a long history of designing lodges and hotels in the national parks and an expert at blending them into the natural terrain, was brought in as a consultant. At Griffith’s urging, the lodge kept getting larger. As it took shape, two wings branched off from a central axis. Cedar shake and clapboard walls rose above a first floor faced with stone. It had steep rooflines that rose sixteen inches for every twelve inches they covered horizontally, so as to shed winter snows that averaged a formidable 250 inches. Dormer windows were set into the roof, and chimneys rose from the roof peak.

Far below the timberline at a spot called Summit Meadows lay the site of an abandoned CCC camp, used by the young corpsmen as a base for planting trees and building hiking trails in Mount Hood National Forest. Here in March 1936, with the calendar if not the weather promising the approach of spring, WPA crews started clearing snow as a prelude to refurbishing the camp to house workers on the lodge. It would also provide a starting point for crews to improve the switchback roads that would carry men and materials up the mountain to the building site, and eventually tourists to the lodge. Plans called for cold-weather tents raised off the ground on wooden platforms, as well as mess tents, cookhouses, a machine shop, a sawmill, and sanitary facilities. Summit Meadows lay near the path of the old Oregon Trail; below it at the base of the mountain was a village called Government Camp, on the highway between Portland and points south and east. It was here that the climb to the timberline, several miles by road and trail, began.

The cold and snow on Mount Hood were apparently more daunting than joblessness as supervisors tried to get construction under way. It was the WPA’s practice to use, wherever possible, native materials so as to save money for labor costs. For the Timberline project, this meant cutting native cedars and hewing cedar shakes for the lodge’s roof and walls, a subproject requiring twenty-seven men to live and work in a remote mountainside camp for sixty days. But by March 12, only two men had appeared, and before the month was out the shake camp was scrubbed and bids for cedar shakes put out on the open market.

On April 23, the snow at Summit Meadow now cleared, twenty WPA hires arrived to begin the camp’s refurbishment but found something missing. This oversight started a chain of telephone calls that went all the way to Harry Hopkins in Washington, and from Hopkins back to the Forest Service at Mount Hood. His request: to borrow some camp stoves to heat the workers’ tents, since WPA procurement had failed to requisition any.

While a shipment of camp stoves was being assembled, a classically trained chef named Albert Altorfer roamed a government warehouse in downtown Portland, checking off chairs, tables, stoves, pots and pans, and dishes and utensils from a list of things he needed. It was a long list. Altorfer had been hired as the head chef for the Timberline work camp, and he would be cooking for 200 or more men at a sitting. These were numbers he was used to; a native of Switzerland who had trained at the Hôtel du Lac in the resort town of Neuchâtel, he had landed in Portland in 1923 and cooked at some of the city’s best restaurants, hotels, and private clubs. He was working as a private chef to Aaron Frank, who owned Meier and Frank, a leading department store, when the stock market crashed in 1929. Even people such as Frank had to tighten their belts, and by 1935, with his resources exhausted, a wife and two daughters to support, and no private jobs available, Altorfer turned to the WPA. The day he applied, he found himself mingling with doctors and lawyers he had seen in his restaurants and dining rooms.

Altorfer followed his pots and pans to Summit Meadow. The stoves from the Forest Service had arrived, and the camp soon took shape. By May it was ready for full-time occupation.

Up the mountain at the timberline, the snow was still eighteen feet deep, but drivers had managed to reach the construction site with snow shovels and tractors and clear the working areas so that the architects and a team of surveyors could map out the final location of the lodge. Each day’s work began with the men riding up the mountain on a sled towed behind a tractor on alligator treads. Where deep snow still remained, the team used probes to detail the site’s topography. They deemed snow cornices jutting over the Salmon River canyon near the original site too dangerous to build near, so they moved 300 yards west to solid ground, where the shape of the land was roughly the same. At the end of their workdays, they skied back down the mountain.

Construction began at last on June 13. Snow still clogged the road up the mountainside, and it fell to Captain C. G. Jones, a Forest Service engineer, to see that it was cleared each day for the transportation of materials and a growing complement of men. He oversaw the job with such a sense of urgency that he quickly acquired a nickname: “Hurry-Up” Jones. The official groundbreaking came a month later. The site was finally clear of snow by then, and officials gathered as Griffith of the WPA and Major James Frankland of the Forest Service wielded ceremonial shovels, cameras snapped, and work on the Timberline Lodge was declared properly begun.

Other books

He's No Prince Charming by LuAnn McLane
Maureen McKade by A Dime Novel Hero
Full Tilt by Neal Shusterman
A Merry Little Christmas by Anita Higman
Tourist Season by Carl Hiaasen
The Fire Chronicle by John Stephens
Black Swan by Bruce Sterling